|
The new Alice Springs to Darwin railway is open for
business. The first south-north transcontinental freight
train to Darwin departed Adelaide on 15 January. The 1.3km-long train, headed by two new 2862kW locos built
by EDI Rail in Port Augusta, attracted huge interest on the three day journey, with many thousands of people
attending public celebrations at key centres and lining the track-side along the route.
Special indigenous artwork on the two new locomotives
recognises the extensive involvement of, and
collaboration with, the Aboriginal communities of the Northern Territory. Northern Land Council (NLC) chief
executive Norman Fry said: 'When we signed the single Land Use Agreement with the NT Government in April 2001
- under which traditional owners gave their consent for the railway to be built on their land - the
consortium and its contractors committed themselves to providing 50 job placements and training for
indigenous workers over the life of the project in the NLC's area. By the end of 2002, more than
150 job placements for Aboriginal workers had been secured with the contractors, and more than
200 Aboriginal people in the NLC's area had participated in railway training programs.'
While the line was built mainly for freight traffic,
a lot of interest has been generated by the
new 2979km transcontinental passenger journey from Adelaide. The first Ghan departed Adelaide on its
inaugural journey to Darwin on 1 February 2004, arriving in Darwin on 3 February.
The train comprised
two locomotives pulling 43 carriages with a total mass of 2000t.
The project is an engineering achievement, with
construction of 1420km of track and 93 bridges being
completed five months early and within budget, for a total cost of $1.4 billion. The private sector
contributed $750 million, while the Federal, SA and NT governments contributed the remainder.
With financial close in April 2001, tracklaying
began in April 2002 with a contracted completion
date of April 2004. Rapid construction saw the final thermit weld at the Alice Springs connection
with the existing line being made on 18 September 2003 and the construction was complete by late October.
The single track standard gauge project required 15 million cubic metres of
earthworks, 1500 culverts,
and 93 bridges including three major structures. For freight the line links with the expanded
Port of Darwin, while an interim passenger facility has been built adjacent to the Darwin Business Park
in Berrimah. Completion of the line brings to fulfilment a 94-year promise. On 1 January 1911 the
Northern Territory was transferred from South Australia to the Commonwealth. As part of the transfer
agreement, with enabling legislation (Northern Territory Acceptance Act 1910) the commonwealth undertook
to 'construct, or cause to be constructed, a railway line from Port Darwin southwards to a point on the
northern boundary of South Australia proper'.
KBR (Kellogg Brown and Root Pty Ltd) was the
driving force behind the creation of Asia Pacific Transport,
the private sector consortium that won the contract to finance, build, maintain and operate the
Alice Springs-Darwin rail link. The other consortium members are John Holland, Barclay Mowlem, Macmahon
and Australian Railroad Group (ARG). ADrail was formed to design and build the railway, FreightLink
was established to operate the rail freight services between Adelaide and Darwin, while BIB will
maintain the railway from Tarcoola (the junction with the east-west line in SA) to Darwin.
As project managers for Trackworks North,
Barclay Mowlem was responsible for 649km of tracklaying.
Commencing in mid-April 200 1, the team initially proceeded southward from Katherine and met the
Tennant Creek based southern trackwork team midway before relocating to Katherine to lay track
north to Darwin, which was completed on 18 September 2003. The team constructed 2.4km of track most days,
well in excess of its scheduled target. Barclay Mowlem also constructed five major bridges spanning the
Katherine, Edith, Adelaide, Cullen and Elizabeth Rivers, the refurbishment of the Fergusson River Bridge
and three Katherine floodplain bridges.
Austrak , a wholly owned subsidiary of
Barclay Mowlem, supplied 2 million concrete sleepers from two
purpose-built factories in Katherine and Tennant Creek.
John Holland was involved in the overall design
and construction of the railway and provided the expertise
for the building of 85 bridges, precasting of bridge structures and management of Trackworks South, which
built the remaining 771km of line.
MacMahon's contribution included project management
and engineering secondment for the line's 15 million
cubic metres of earthworks and drainage; sourcing of construction materials and water; remote area logistics;
equipment maintenance; the provision of the large earthmoving fleet and much of the labour for the earthworks
component.
ARG was contracted to provide train services for the
construction of the rail- way. From the commencement of
regular operations ARG operates freight trains between Adelaide and Darwin on behalf of FreightLink. ARG
provides crews, rail infrastructure services (which include train control and safe-working management) and
general technical support to FreightLink as well as being the accredited operator. ARG manages all safeworking
between Tarcoola and Darwin for all rail operators and maintainers. ARG also provides rolling stock to
FreightLink with the supply of four locomotives and initially up to 100 container wagons.
The key focus for the freight operation business plan
recognises the rail- way's important role in the
NT government's ambitions to promote Darwin as Australia's Asian gateway. FreightLink will run five freight
trains per week of up to 1.8km in length, increasing to six services as customer demand increases.
FreightLink CEO Bruce McGowan said:
'The first major business for the new line is expected to be existing Darwin-bound freight, which went
to Alice Springs by rail and then north by road. Up to 350,OOOt of fuel and general products are already
carried by road and rail. There is potential to increase this to over 800,OOOt during the first few years
of operations. Darwin's proximity to the burgeoning Asian markets to our immediate north provides an
exciting opportunity for an alternative trade route. The NT capital is the obvious centre for trade
between the busy markets of Australia's southeast and ports in Asia. Singapore, our seventh largest bilateral
trading partner, is about four days away by sea; Hong Kong and Port Klang are five.' McGowan said.
KBR's senior international vice-president
Andrew Fletcher said: 'Opening this landbridge to Asia will create
exciting opportunities both domestically and internationally, boosting both economic development and trade.
This is a long- term project, and KBR is in it for the long haul. The Alice to Darwin Railway has inspired
many great innovations, for example, clever, modular bridge designs by KBR's engineers which enabled
93 bridges to be built at an average of one bridge a week. The logistics of managing a significant
workforce in a harsh environment, placing more than 25,000 orders for goods and services, and synchronising
the movement of millions of tonnes of earth, sleepers and rails have called for great precision. We're proud
that the expertise to achieve projects of this magnitude is Australian.' he said.
Managing Director of John Holland Bill Wild said:
'More than 5.5 million man hours, involving over 1100 people, demonstrated to the world that the Australian construction industry can manage infrastructure projects of a
truly massive scale. Add to that the fact that the many teams involved in the project came from all around
the nation and worked on a site about 1420km in length - which few projects in the world could boast.
Landmark projects like this don't come along all that often'.
Credit - Engineer Australia 2004 |